Yesterday Cody (our plumber) and Pat (our electrician) got the boiler and in-floor heating going. Hopefully this week they will get the furnace and pumping system working.
The finishing work is well on its way to completion. All of the drawers, shelves and counter tops have been installed in the cabinets and vanities. The next phase for them is doors, drawer fronts, crown molding and trim.
Kitchen Cabinets.
Laundry Cabinets.
Master Bathroom Vanities.
Chad and Mike continue with all of the interior finishing work (hanging interior doors, baseboards and casement). They have made great progress and the basement is nearly ready for painting and they think that the upstairs won't take to long to hang the doors and do the casing around the windows.
Closet Doors in Downstairs Bedroom with Closet Organizer.
(Chad and Mike's Work)
This downstairs bedroom only needs the window casement installed and it's ready for paint and carpet.